Stairs Installed

Posted by tom | Nov 17, 2006

Just a quick update, pics coming but I have to get some rest . . .

The pumping of the concrete into the basement went fine on Thursday. Good thing that we had already covered the windows as 'the rains came down and the floods came up.' We also had to eventually cover the entrances. The electric inspection occurred today, ready for PP&L :-) The steps, the doors, and the double basin utility sink were delivered and mostly installed today. Tomorrow Carl and I will work on the water pump, finish the one door, finish the sink, pick-up the dryer, etc.

HVAC and backfill will begin on Monday. After backfill, the excavator will work on the driveway, necessary for occupancy, and the deck out of the first floor back, if necessary for occupancy (we've received conflicting stories). Hopefully the windows will arrive by early December, should have ordered them on our own. The cable will arrive sometime in the next 2 weeks. Vonage is up and running.